We are happy to inform you that one of our most ambitious projects of the year is already in action. During the course of May, Tradelossa has been transporting multiple transformers from the north of Mexico to several states within the U. S. territory. The first two transformers traveled from the city of Apodaca,…
We have successfully finished the delivery of all components for EVM II Project in Mexico. This included the transportation of 29 BOPs and multiple accessories. In total, we moved 131 trucks, which translates to 2.67 Million Pounds (1.21 million kilograms) traveling about 138,800 miles (223,388 kilometers) in six months. For this project, we were able to…
Tradelossa has concluded the transportation of transformers of 192 tons each for the Cycle Power Plant in Los Ramones, Nuevo Leon. Transformers transportation has historically been an area of expertise for Tradelossa and this month couldn’t be an exception concluding the delivery of two components of 9. 40 meters long, 3. 82 meters wide and 4.32 meters…
The second month of the year has ended and Tradelossa continues to meet new goals and overcome new challenges. Our teams have completed the delivery of two steel shell plates across the country. The pieces were departed from an industrial park in Apodaca, Nuevo Leon and delivered in Lazaro Cardenas, Michoacan, making a journey from…
We were involved in the transportation of two gas turbines and two gas generators for “Los Ramones” Project. The reception was done from a Rail Car to the Faktor 5, using skidding techniques. The jacking equipment was positioned aside the rail to complete the loading to our hydraulic equipment. After the successful performance from our…
We have successfully completed all heavy cargo deliveries for the project in Tierra Mojada. Our scope included the transportation of two GT’S, GTG’s, LH, UH Machining components and a steam generator. In total, we move 12 freights, which meant moving 3,400,000 pounds and traveling more than 8077 miles. During this time we were able to travel…
We have finished with the transportation of all the components for the Combined Cycle Power Plant in El Carmen, Nuevo León. Tradelossa has performed the transportation of two sets of generators and gas turbines, as well as the assembly of a generator and a steam turbine, making use of the 500-ton gantry and Strand Jack…
We have successfully completed the transportation and rigging of two generators and a steam turbine for the project Norte III. During the last month, we collaborated once again in the Norte III project located in Samalayuca, Chihuahua. Our role in the project began with the reception and loading of both generators and a steam turbine,…