This time we completed the Emerging Energy Project which will have the capacity of 110MW, located in Aquiles Serdan, Chihuahua.
At the beginning of July, we received twelve Gensets inside the port of Altamira, Tamaulipas; The transportation of all Gensets were carried out in two convoys with six on each group, making use of our modular lines we place the six Gensets on our trucks and travel 1600 km, each convoy.
Once we arrive at the project site, the Gensets were unloaded using our Gantry and Jack & Slide equipment.
The project was completed in compliance with all the regulations and safety measures that apply both, the port of Altamira and the plant on Chihuahua.
The dimensions of the Gensets were:
13 meters length, 3.35 meters width, 4.50 meters height; weighing 140 tons each.
This has been a project consisted of the reception, transport, and rigging job that has been carried out over 32 days of work and continuous coordination between our logistic and field team, and client.