We were involved in the transportation of two gas turbines and two gas generators for “Los Ramones” Project. The reception was done from a Rail Car to the Faktor 5, using skidding techniques.
The jacking equipment was positioned aside the rail to complete the loading to our hydraulic equipment. After the successful performance from our rigging team, we began with the transportation process from Apodaca to the project site in Los Ramones, Nuevo Leon.
Two (2) Gas Turbines of 10.10 meters length, 4.40 meters width, 4.40 meters height, weighing 257 tons.
Two (2) Gas Generators of 8.20 meters length, 3.90 meters width, 4.20 meters height, weighing 291 tons
As one team, Tradelossa always worked very hard to guarantee that the cargo was delivered safely and on time.